Hi Dieter ,



Thank you very much for your help . It works now .



Regards



Jia yin

Member for

18 years 9 months

Hi Jia

I’m not sure if I really got your question.

Have a look under Edit --> User Preferences --> resource analysis. The last line is "Interval for resource calculations". There you entered "Month", I suppose. Then the smallest intervall for calculations will be the month. Change it into days or week - depends on your reporting needs.

Hope, this will help.