Have a look under Edit --> User Preferences --> resource analysis. The last line is "Interval for resource calculations". There you entered "Month", I suppose. Then the smallest intervall for calculations will be the month. Change it into days or week - depends on your reporting needs.
Member for
18 years 7 monthsRE: Report
Sorry , Wrong face....
Member for
18 years 7 monthsRE: Report
Hi Dieter ,
Thank you very much for your help . It works now .
Regards
Jia yin
Member for
18 years 9 monthsRE: Report
Hi Jia
Im not sure if I really got your question.
Have a look under Edit --> User Preferences --> resource analysis. The last line is "Interval for resource calculations". There you entered "Month", I suppose. Then the smallest intervall for calculations will be the month. Change it into days or week - depends on your reporting needs.
Hope, this will help.
Dieter