Displaying delay of tasks graphically

Member for

18 years 5 months



I also agree.

But, what about Technical % complete on a task. Do someone use this data on GANTT chart?



Kindest regards.

Patricia

Member for

18 years 8 months

Ijaz,

I would use either the original baseline bar and the current bar on the GANTT or see if you can create a special bar by using user_start_date fields filtered on critical activities in conjunction with a global change.



You could populate the start date with the baseline start/finish, and the finish date with the actual/planned start/finish.



Andy