I would use either the original baseline bar and the current bar on the GANTT or see if you can create a special bar by using user_start_date fields filtered on critical activities in conjunction with a global change.
You could populate the start date with the baseline start/finish, and the finish date with the actual/planned start/finish.
Member for
18 years 5 monthsRE: Displaying delay of tasks graphically
I also agree.
But, what about Technical % complete on a task. Do someone use this data on GANTT chart?
Kindest regards.
Patricia
Member for
18 years 6 monthsRE: Displaying delay of tasks graphically
I agree, baseline and the current bar on the Gantt is the best way.
Member for
18 years 8 monthsRE: Displaying delay of tasks graphically
Ijaz,
I would use either the original baseline bar and the current bar on the GANTT or see if you can create a special bar by using user_start_date fields filtered on critical activities in conjunction with a global change.
You could populate the start date with the baseline start/finish, and the finish date with the actual/planned start/finish.
Andy