the simple thing is in p5 we cannot import/export a project with its baseline, we have to follow all the cumbersome process as described in the thread P3e - Project export without Baseline!!!
so one of the most bulls**t thing of p5.
hail the primavera people, long live p5 and primavera for creating such kind of mess.
cheers
mangesh
Member for
21 years 4 months
Member for21 years4 months
Submitted by Benito Nepomuceno on Tue, 2007-08-07 04:35
Your inquiry was posted in the previous thread titled "Migrating from P3e V4.1 to V5.0". You cannot export the baseline unless you "restore" it and export it seperately.
Member for
20 years 7 monthsRE: P3e - Project import without Baseline!!!
Mangesh,
Primavera have probably heard your @^#!@&s because P6 allows you import and export baselines along with your project.
H.T.H.
Member for
18 years 7 monthsRE: P3e - Project import without Baseline!!!
hi
the simple thing is in p5 we cannot import/export a project with its baseline, we have to follow all the cumbersome process as described in the thread P3e - Project export without Baseline!!!
so one of the most bulls**t thing of p5.
hail the primavera people, long live p5 and primavera for creating such kind of mess.
cheers
mangesh
Member for
21 years 4 monthsRE: P3e - Project import without Baseline!!!
Hi Mangesh,
Your inquiry was posted in the previous thread titled "Migrating from P3e V4.1 to V5.0". You cannot export the baseline unless you "restore" it and export it seperately.
benito