P3e - Project import without Baseline!!!

Member for

20 years 7 months

Mangesh,



Primavera have probably heard your @^#!@&’s because P6 allows you import and export baselines along with your project.



H.T.H.

Member for

18 years 7 months

hi

the simple thing is in p5 we cannot import/export a project with its baseline, we have to follow all the cumbersome process as described in the thread P3e - Project export without Baseline!!!



so one of the most bulls**t thing of p5.

hail the primavera people, long live p5 and primavera for creating such kind of mess.



cheers



mangesh

Member for

21 years 4 months

Hi Mangesh,



Your inquiry was posted in the previous thread titled "Migrating from P3e V4.1 to V5.0". You cannot export the baseline unless you "restore" it and export it seperately.



benito