- Supervised the construction process from the conceptual development stage through final construction, made sure that the project gets done on time and budget
- Responsible for preparing tender programme for plenty of different types of construction projects i.e. residential & public buildings, roads & bridges, mega water reservoirs & associated pipeline works, marine works and railway projects
- Finalized the working methodologies with the technical team before the programme is developed; also created manpower histogram and cash inflows to find out the resource availability and different options to arrange the remaining resource
- Transformed the tender documents to contract documents, upon the award of the project; collaborated with the site planners and the client to receive the approvals
- Generated the internal progress measurement system to monitor the progress and performance; tracked the different delay events and prepared the EOT claims
- Worked in the capacity of In-charge of the Project “People Mover System”, a 12 km long tram line in Education City, Doha in consortium with Siemens
Experience Hours (Planning & Scheduling):
10000
Experience Hours (Cost Management):
2000
Experience Hours (Forensic Analysis):
1000
Links:
[1] http://www.planningplanet.com/category/skills-expertise/100-project-planning-progress-reporting-ms-project-master-schedule-and-cla
[2] http://www.planningplanet.com/category/industry/civil-building-em
[3] http://www.planningplanet.com/category/training/different-leadership-trainings
[4] http://www.planningplanet.com/category/job-role/group-head-planning-and-scheduling
[5] http://www.planningplanet.com/category/company/leighton-contracting-qatar
[6] http://www.planningplanet.com/category/project/mega-water-reservoirs-and-pipeline-works-qatar-water-26-electricity-department
[7] http://www.planningplanet.com/category/project/people-mover-system-tram-project
[8] http://www.planningplanet.com/taxonomy/term/13613
[9] http://www.planningplanet.com/category/project/shopping-mall
[10] http://www.planningplanet.com/category/region/middle-east-region/asia/qatar-asqa