Lahore Islamabad Motorway Project, Pakistan 350 Km, 6 Lane Motorway with Approach Roads, underpasses, bridges, utilities, Flyovers and Underpasses (Cost > 1 Billion US $)
• developed schedules of work and updated the progress
• monitored the works of sub-contractors and calculated /approved the payment of executed works;
• recorded and updated progress compared theoretical with actual works;
• measured monthly quantities of executed and prepared measurement sheets;
• reported / updated progress, prepared as-built drawings, charts, presentations showing activities at site;
• developed / maintained database of work progress, correspondence, inventory and staffing;
• Processed and execute site survey data, uploaded, downloaded and developed site layouts , generated x-sections, layouts, profiles and comparison of actual with design.