Planner for Exchanger & Furnace Maintenance works in TA-2007 under BAPCO planning team
- Preparation of T/A hourly schedule base line schedule
- Resource Loading and resource levelling
- Preparation of 'S' Curve based on Man-hours
- Monitoring the progress in Hourly basis.
- Preparation of Daily progress report & area of concern
- Analyze the critical activity and found the solution with Bapco shutdown team & shutdown engineer.
- Preparation of variation for additional scope, which is found during the maintenance