START Date:
August, 2005
END Date:
April, 2006 - Review and update all project fabrication scope utilising in house resources and facilities to enable management to maintain staffing continuity and production efficiency.
- Maintain & update fabrication progress for offsite projects at ConocoPhillips Humber Refinery and UK Interconnector at Bacton.
- Review and Develop level 2 programs for Tender Work along with projected resourcing levels.
- Review and develop program, all planning progress trackers and contractual documentation for ConocoPhillips VOC Recovery Project, Teesside.