START Date:
February, 2009
END Date:
July, 2009 • Attended pre-construction meetings and assisted in the planning process.
• Studied drawings, quantity take off and preparation of preliminary schedules.
• Prepared temporary site layout schemes & site logistic plans.
• Prepared design programmes for different work packages and identified major interfaces between packages.
• Prepare & issued stage programmes.
• Attend meetings and collaborative workshops with contractors to identify interfaces and highlight criticality of interdependencies.
• Underwent training in ‘Asta Power Project’.
• Played a vital role in redefining planning related procedures- both pre and post contract procedures.
• Studied drawings, quantity take off and preparation of preliminary schedules.
• Prepared temporary site layout schemes & site logistic plans.
• Prepared design programmes for different work packages and identified major interfaces between packages.
• Prepare & issued stage programmes.
• Attend meetings and collaborative workshops with contractors to identify interfaces and highlight criticality of interdependencies.
• Underwent training in ‘Asta Power Project’.
• Played a vital role in redefining planning related procedures- both pre and post contract procedures.