Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Cost Accounts and the Activities Screen

No replies
Marc Timberlake
User offline. Last seen 3 weeks 5 days ago. Offline
Joined: 11 Feb 2019
Posts: 5
Groups: None

Hi,

we're looking to make use of Cost Accounts within our projects, and I have a small question to ask of the experts.

 

If we have two resource IDs on an activity, both with the same cost account allocated - is there a way for the activity to be grouped with other activities with the same?

Currently I get as far as the below screenshot, and it keeps them separate.

Any ideas much appreciated

8648
screenshot_2024-04-17_171813.png

Renzo Constenla B...
User offline. Last seen 2 weeks 4 days ago. Offline
Joined: 23 Mar 2011
Posts: 18

Hi

 

in the Activities windos, for the layout use the Group & Sort icon, starting with Accounts ID.

regards

 

Marc Timberlake
User offline. Last seen 3 weeks 5 days ago. Offline
Joined: 11 Feb 2019
Posts: 5
Groups: None

Thanks,

ideally I'd like to be able to output earned value data at cost account level, but due to version we currently use it's not an available field on the resources tab. We'll be upgrading soon, so can make better use.

Marc Timberlake
User offline. Last seen 3 weeks 5 days ago. Offline
Joined: 11 Feb 2019
Posts: 5
Groups: None

Thanks,

ideally I'd like to be able to output earned value data at cost account level, but due to version we currently use it's not an available field on the resources tab. We'll be upgrading soon, so can make better use.

david kelly
User offline. Last seen 6 days 5 hours ago. Offline
Joined: 12 Feb 2016
Posts: 33
Groups: None

Cost account is an attribute of the Resource Assignment and Expenses tables. Therefore, you should be in the Resource assignment rather than Activities window to group by Cost account. Of course, you then cannot list activities without a resource.

 

Note: There is no 'Cost' Window, because P6 was never actually finished, just sort of abandoned when Oracle bought it

There is no 'Resource/Cost barchart' like P3 could do in 1995, because it was never finished.

The only way to see costs from expenses and resource assignments on one report is using the tabular reports