Alternatives to lags and dummy activities

Member for

16 years 3 months

add the activites that get you from engineering to installation

Member for

19 years 10 months

Hi Brian

Set up a sub chart and put the tasks and duration into a procurement cascade.

Then link the last task to your installation task - you will have some float availabl.

Best regards Mike Testro

Member for

22 years 9 months

Brian,

When I was working for the US State Dept, I was not allowed to use lead, lags and date constraints; I used dummy tasks instead.

You could assign a specific calendar to these dummy tasks, e.g. 7/7 or 24/24

Alexandre