Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2020-04-30 13:43 Permalink add the activites that get add the activites that get you from engineering to installation Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Thu, 2020-04-30 10:05 Permalink Hi BrianSet up a sub chart Hi Brian Set up a sub chart and put the tasks and duration into a procurement cascade. Then link the last task to your installation task - you will have some float availabl. Best regards Mike Testro Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Thu, 2020-04-30 09:46 Permalink Brian,When I was working for Brian, When I was working for the US State Dept, I was not allowed to use lead, lags and date constraints; I used dummy tasks instead. You could assign a specific calendar to these dummy tasks, e.g. 7/7 or 24/24 Alexandre Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2020-04-30 13:43 Permalink add the activites that get add the activites that get you from engineering to installation
Member for 19 years 10 months Member for 19 years 11 months Submitted by Mike Testro on Thu, 2020-04-30 10:05 Permalink Hi BrianSet up a sub chart Hi Brian Set up a sub chart and put the tasks and duration into a procurement cascade. Then link the last task to your installation task - you will have some float availabl. Best regards Mike Testro
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Thu, 2020-04-30 09:46 Permalink Brian,When I was working for Brian, When I was working for the US State Dept, I was not allowed to use lead, lags and date constraints; I used dummy tasks instead. You could assign a specific calendar to these dummy tasks, e.g. 7/7 or 24/24 Alexandre
Member for
16 years 3 monthsadd the activites that get
add the activites that get you from engineering to installation
Member for
19 years 10 monthsHi BrianSet up a sub chart
Hi Brian
Set up a sub chart and put the tasks and duration into a procurement cascade.
Then link the last task to your installation task - you will have some float availabl.
Best regards Mike Testro
Member for
22 years 9 monthsBrian,When I was working for
Brian,
When I was working for the US State Dept, I was not allowed to use lead, lags and date constraints; I used dummy tasks instead.
You could assign a specific calendar to these dummy tasks, e.g. 7/7 or 24/24
Alexandre