1. view show on bottom resource usage profile lower right are right click resource usage profile options
click units
for the ASAP curve click remaining early box
for the ALAP curve click the remaining late box
2. The durations should be as long as it takes based on the quantity of brick work to install divided by the production rate divided by the number of brick layers i.e. 1000 bricks to lay standard rate is 1 man 500 bricks per day
so 1000/500 = 2 days for 1 man or 1000/1000 = 1 day for 2 men
3. whats the cost for the material ? whats the cost for the labor ?
material cost would be wire, panles and fixtures
labor cost would be manhours multimplied bty the labor rate
total cost would be material + Labor
add an electrican resource and put the cost in as the total of the material and labor
Member for
16 years 3 months1. view show on bottom
1. view show on bottom resource usage profile lower right are right click resource usage profile options
click units
for the ASAP curve click remaining early box
for the ALAP curve click the remaining late box
2. The durations should be as long as it takes based on the quantity of brick work to install divided by the production rate divided by the number of brick layers i.e. 1000 bricks to lay standard rate is 1 man 500 bricks per day
so 1000/500 = 2 days for 1 man or 1000/1000 = 1 day for 2 men
3. whats the cost for the material ? whats the cost for the labor ?
material cost would be wire, panles and fixtures
labor cost would be manhours multimplied bty the labor rate
total cost would be material + Labor
add an electrican resource and put the cost in as the total of the material and labor