1. view show on bottom resource usage profile lower right are right click  resource usage profile options 

click units

for the ASAP curve click remaining early box

for the ALAP curve click the remaining late box

2. The durations should be as long as it takes based on the quantity of brick work to install divided by the production rate divided by the number of brick layers i.e. 1000 bricks to lay standard rate is 1 man 500 bricks per day

so 1000/500 = 2 days for 1 man or 1000/1000 = 1 day for 2 men 

3. whats the cost for the material ? whats the cost for the labor ?

material cost would be wire, panles and fixtures

labor cost would be manhours multimplied bty the labor rate 

total cost would be material + Labor

add an electrican resource and put the cost in as the total of the material and labor