Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2022-02-25 13:30 Permalink check the specifications check the specifications sometimes bids are locked in for a specific period of time. But I have not seen at as long as 6 months. Yes you, your subs and the 3rd tier subs would have to provide back up for escalation Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Fri, 2022-02-25 13:30 Permalink check the specifications check the specifications sometimes bids are locked in for a specific period of time. But I have not seen at as long as 6 months. Yes you, your subs and the 3rd tier subs would have to provide back up for escalation
Member for
16 years 3 monthscheck the specifications
check the specifications sometimes bids are locked in for a specific period of time. But I have not seen at as long as 6 months.
Yes you, your subs and the 3rd tier subs would have to provide back up for escalation