19 yearsHi Sharjeel,Depending on how
Hi Sharjeel,
Depending on how the master schedule is setup and what is the company policy and procedures for Master Schedule.
Some company procedure requiring Level 3 for integrated Master Schedule and Level 4 & Level 5 for contractors schedule.
You can code the contractor's level 4 or level 5 to match Master Level 3 schedule for easy update.