Monthly Mitigation Meetings

Member for

12 years 2 months

Great, thanks for your reply!

 

Cheers,

 

Tom

Member for

16 years 3 months

1. Assessment of previous mitigation plan (is this is 1st meeting there will not be any) did things work or not ? Waht was done right what could be improved. 

2. Current Overall status of the Project.

3. Any impediments such as lack of Design, lack of Access, Late Material delivery, Shortage of Manpower, submittals, RFI's or change notices that are hot and have a potential to hold up work.

4. Review of the Current Critical Path and Next weeks path. 

5. Areas that require special attention or that are behind schedule.

6. Key Contractors who will be responsible for the mitigation.

7. Summary plan for mitigation  ie. working longer hours, working more days, more manpower or different logic and or sequence.

8. Set meeting time and date for deep dive of mitigation plan (approx 1 week from this meeting).