This option displays the spread for the data item (selected under Time Interval Fields button in above dialog) for each time interval (selected under Timescale button in above dialog) from the timescale start date to the timescale finish date (selected under Timescale button in above dialog).
In the report above we have selected to display the Remaining Units by week for the month of November.
Show Prior
This option displays the cumulative value before the first time interval.
In the report above, the Project Manager had accumulated 40 days and 4 hours of Remaining Units before the first week in November.
Member for
22 years 9 monthsHello,this post should have
Hello,
this post should have been entered in the Primavera P6 forum
more and more questions are posted in this General forum, please do not do that
Thank you,
Alexandre
Member for
16 years 3 monthsneed your email address to do
need your email address to do that
Member for
10 years 3 monthsI could not open image that
I could not open image that you attached please send it to me
Member for
10 years 3 monthsMany thanks
Many thanks
Member for
10 years 3 months......
......
Member for
16 years 3 monthszcapture.jpg Show Time
This option displays the spread for the data item (selected under Time Interval Fields button in above dialog) for each time interval (selected under Timescale button in above dialog) from the timescale start date to the timescale finish date (selected under Timescale button in above dialog).
In the report above we have selected to display the Remaining Units by week for the month of November.
This option displays the cumulative value before the first time interval.
In the report above, the Project Manager had accumulated 40 days and 4 hours of Remaining Units before the first week in November.