Planning, Scheduling & Programming Discussion Member for 14 years 5 months Member for 14 years 5 months Submitted by soohyla on Fri, 2020-03-20 01:43 Permalink Zoltan, thank you for your Zoltan, thank you for your affirmation. Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2020-03-19 12:09 Permalink Suhaila that is correct Suhaila that is correct Member for 14 years 5 months Member for 14 years 5 months Submitted by soohyla on Thu, 2020-03-19 01:27 Permalink Dear All 1. A schedule which Dear All 1. A schedule which is not correctly or completely loaded cannot produce a complete plan%, right? 2. A schedule need to be cost loaded in order to get the schedule % complete at the WBS level and at the total roll-up. Member for 7 years 5 months Member for 7 years 5 months Submitted by Joseph Mbogo on Tue, 2020-01-07 11:09 Permalink Build a matrix driven by Build a matrix driven by Cost, Duration, Resources (Manpower) requirements. The Weightage then will be clear where you have more and less. Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2019-12-16 15:22 Permalink whats your measuring stick whats your measuring stick ? The Idea takes time a Study Takes time the Design takes time the Implementation takes time what do all of these have in common ? TIME how is time measured ? Usually in manhours So figured out the manhours for each of these stages and you have your weights Log in or register to post comments
Member for 14 years 5 months Member for 14 years 5 months Submitted by soohyla on Fri, 2020-03-20 01:43 Permalink Zoltan, thank you for your Zoltan, thank you for your affirmation.
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2020-03-19 12:09 Permalink Suhaila that is correct Suhaila that is correct
Member for 14 years 5 months Member for 14 years 5 months Submitted by soohyla on Thu, 2020-03-19 01:27 Permalink Dear All 1. A schedule which Dear All 1. A schedule which is not correctly or completely loaded cannot produce a complete plan%, right? 2. A schedule need to be cost loaded in order to get the schedule % complete at the WBS level and at the total roll-up.
Member for 7 years 5 months Member for 7 years 5 months Submitted by Joseph Mbogo on Tue, 2020-01-07 11:09 Permalink Build a matrix driven by Build a matrix driven by Cost, Duration, Resources (Manpower) requirements. The Weightage then will be clear where you have more and less.
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Mon, 2019-12-16 15:22 Permalink whats your measuring stick whats your measuring stick ? The Idea takes time a Study Takes time the Design takes time the Implementation takes time what do all of these have in common ? TIME how is time measured ? Usually in manhours So figured out the manhours for each of these stages and you have your weights
Member for
14 years 5 monthsZoltan, thank you for your
Zoltan, thank you for your affirmation.
Member for
16 years 3 monthsSuhaila that is correct
Suhaila that is correct
Member for
14 years 5 monthsDear All 1. A schedule which
Dear All
1. A schedule which is not correctly or completely loaded
cannot produce a complete plan%, right?
2. A schedule need to be cost loaded in order to get the schedule % complete at the WBS level and at the total roll-up.
Member for
7 years 5 monthsBuild a matrix driven by
Build a matrix driven by Cost, Duration, Resources (Manpower) requirements.
The Weightage then will be clear where you have more and less.
Member for
16 years 3 monthswhats your measuring stick
whats your measuring stick ?
The Idea takes time
a Study Takes time
the Design takes time
the Implementation takes time
what do all of these have in common ? TIME
how is time measured ?
Usually in manhours
So figured out the manhours for each of these stages and you have your weights