Primavera can calculate EV and PV only for each activitiy if it is loaded in hours (labor units) but he cannot give the EV or PV in the WBS summary of the activities unless you assign the PRICE/UNIT equals to 1.
Member for
16 years 3 months
Member for16 years4 months
Submitted by Zoltan Palffy on Mon, 2020-03-09 13:46
Member for
5 years 9 monthsPrimavera can calculate EV
Primavera can calculate EV and PV only for each activitiy if it is loaded in hours (labor units) but he cannot give the EV or PV in the WBS summary of the activities unless you assign the PRICE/UNIT equals to 1.
Member for
16 years 3 monthsJust go to columns and add a
Just go to columns and add a column it is under earned value its called Earned Value Labor Units