Hi Joseph,

Your fundamental proposition is completely flawed. 

1. Agile is a product development methdodolgy (ie, a way to organise people to achieve the work needed for a development). Waterfall is a product development methdodolgy (ie, a way to organise people to achieve the work needed for a development).  

Planning in either an Agile development or a Waterfall development needs to reflect the methodology being used. Deciding on the best methodology is a strategic decision: https://mosaicprojects.com.au/WhitePapers/WP1038_Strategy.pdf 

2. Planning, scheduling and maintaining the schedule is a project controls process.  Whereas contract administration is largely a financial controls process.  One person may do both jobs (I certainly used to on construction sites) but the purpose of planning, monitring and updating is to provide infomration to the project manager to help manage the work of the project going forward.  The funtion of contract administration is to make sure contractors do what they are supposed to do (which inculdes working to the plan) and making sure they are paid correctly. For mrore on project controls see: https://mosaicprojects.com.au/WhitePapers/WP1093_Project_Controls.pdf