1 Project - 2 Contractor - Import of Data

Member for

16 years 3 months

no next month when you get the schedule and if you follow my instruction you see that it is a different 

next month when you get the updated schedules copy the master schedule 

take the civil schedule and import it but this time during the import process where it say Import Project Options click in the IMPORT ACTION box select UPDATE EXISTING

after that 

take the MEP schedule and import it but this time during the import process where it say Import Project Options click in the IMPORT ACTION box select UPDATE EXISTING

during the import process you can pick and choose what and how to import data

when you get to the Update Project Options select MODIFY

this is where you can select Update Existing, Keep Existing or Do not import for the global data as well as the project data.

Member for

14 years 7 months

Thanks Everyone,

So when you import the Resource and Cost also would be imported ?

 

After importing I have to link the Civil to the MEP Schedule, so then it becomes the master schedule.

 

So everytime when both of the Contractor update the schedule and I import it to the master schedule, the master scheduel would be updated too.

 

Regards

Jithin

Member for

20 years 6 months

Just open both project schedules at the same time. Use a common Activity coding structure for both and it can appear to be a single schedule. 

Now getting the links an the logic across both schedules is a different issue!

Member for

15 years 11 months

Jithin use the Reflection function as this was made by Primavera for that purpose.

 

Regards,

Member for

16 years 3 months

The key is preparation and is to make sure that they both use the same WBS structure and that the DONOT use the same activity id number I would come up with a nomenclature to use such as all civil activities begin with the letter C and all mep activities begin with the letter M. If it is not like this to begin with you can easily create a global change to add a prefix to an activity id. 

also if you are using activity codes make sure that they are using the same coding structure. 

import one schdeule straigth up as it is and use that as the master lets say you use the civil schedule as the master

have the civil project open and select file import

and then select the MEP project 

during the import process where it say Import Project Options click in the IMPORT ACTION box select ADD TO EXISTING

this will add the MEP project into the civil project and now you will have a master project

if the wbs is different you can move or re-assign the mep activities to the proper wbs location.

now you need to make the relationship links between the civil activities and the MEP activities and re-calcuate the schedule.

next month when you get the updated schedules copy the master schedule 

take the civil schedule and import it but this time during the import process where it say Import Project Options click in the IMPORT ACTION box select UPDATE EXISTING

after that 

take the MEP schedule and import it but this time during the import process where it say Import Project Options click in the IMPORT ACTION box select UPDATE EXISTING

during the import process you can pick and choose what and how to import data

when you get to the Update Project Options select MODIFY

this is where you can select Update Existing, Keep Existing or Do not import for the global data as well as the project data.