Planning, Scheduling & Programming Discussion Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2019-06-18 14:19 Permalink glad I could help glad I could help Member for 9 years 7 months Member for 9 years 7 months Submitted by philipjames on Tue, 2019-06-18 09:52 Permalink Hi ZoltonThank you, thats Hi Zolton Thank you, thats what I thought Philip Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2019-06-06 14:04 Permalink its bascially all reated its bascially all reated projects or none go to tools schedule click on the options button at the top uncheck ignore relationships to and from other projects Log in or register to post comments
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Tue, 2019-06-18 14:19 Permalink glad I could help glad I could help
Member for 9 years 7 months Member for 9 years 7 months Submitted by philipjames on Tue, 2019-06-18 09:52 Permalink Hi ZoltonThank you, thats Hi Zolton Thank you, thats what I thought Philip
Member for 16 years 3 months Member for 16 years 4 months Submitted by Zoltan Palffy on Thu, 2019-06-06 14:04 Permalink its bascially all reated its bascially all reated projects or none go to tools schedule click on the options button at the top uncheck ignore relationships to and from other projects
Member for
16 years 3 monthsglad I could help
glad I could help
Member for
9 years 7 monthsHi ZoltonThank you, thats
Hi Zolton
Thank you, thats what I thought
Philip
Member for
16 years 3 monthsits bascially all reated
its bascially all reated projects or none
go to tools schedule
click on the options button
at the top uncheck ignore relationships to and from other projects