I have the same problem, my Performance Pecentage complete is higher than my last update after changing the baseline and my schedule % complete is way to high. Last week I managed to move % correctly but the other section of the work was not properly resourced, then after fully resourcing the programme is not allowing to adjust the % to the previous %. The % is higher than the previous baseline % by far. Does anyone know what migh be wrong, I have worked on actual cost of the resource still the overall and WBS percentange is not moving. I also checked that % Duration type and Duration type is the same for all activies in the project, Is there any setting which I can amend to make my pecent to move.
I also have the same problem, i have a new schedule prepared from the current schedule for EOT. Now the schedule % complete is not matching the performance %. The performance % is correct the schedule % is less than the performance % i need to bring to schedule % same as the performace to have a proper forecast. Kindly put your ideas
Member for
16 years 7 months
Member for16 years7 months
Submitted by Gary Whitehead on Fri, 2015-05-22 16:30
I agree with you that the Schedule % complete is generated automatically but my question is that "What are the ways to adjust Schedule % Complete on our desired percentage" out of the respect that the mean of software would be negligated. i need to show false schedule % complete
Member for
13 years 8 months
Member for13 years9 months
Submitted by ali.elsayed556 on Tue, 2015-05-19 13:16
first what is the meaning of Schedule % Complete & Performance % complete in Primavera P6
Schedule % Complete means the percentage of elapsed time to the original time (dates wise) i mean if there is an activity with planned started 1apr2015 and planned finish 30apr2015 and the data date is 15apr2015, then the elapsed planned (scheduled) time to the planned duration (30 days) will be 50 %. it present the schedule % complete. if you have completed for example 50 % of the quantity of work, then your Performance % complete is 50 % then you are on schedule . but if you finished 40 % then your performance is 40 % but you have finished 50 % of your planned duration which means you are behind the schedule. and like that
Schedule % complete can't be changed as it automatically generated.
Member for
9 years 1 monthHi AllI have the same
Hi All
I have the same problem, my Performance Pecentage complete is higher than my last update after changing the baseline and my schedule % complete is way to high. Last week I managed to move % correctly but the other section of the work was not properly resourced, then after fully resourcing the programme is not allowing to adjust the % to the previous %. The % is higher than the previous baseline % by far. Does anyone know what migh be wrong, I have worked on actual cost of the resource still the overall and WBS percentange is not moving. I also checked that % Duration type and Duration type is the same for all activies in the project, Is there any setting which I can amend to make my pecent to move.
Thanks
K. R
T.D
Member for
10 years 4 monthsPossibly, but my
Possibly, but my requirement is urgent and has nothing to do un proffessional i seee it as a p6 glitch. So if someone know kindly let me know
Member for
15 years 11 monthsI know how to adjust it but
I know how to adjust it but as Garry said it can be misused.
Member for
10 years 4 monthsHi I also have the same
Hi
I also have the same problem, i have a new schedule prepared from the current schedule for EOT. Now the schedule % complete is not matching the performance %. The performance % is correct the schedule % is less than the performance % i need to bring to schedule % same as the performace to have a proper forecast. Kindly put your ideas
Member for
16 years 7 monthsYes, there are ways to lie
Yes, there are ways to lie about your % complete in Primavera.
but I'm not going to tell you what they are, because I don't like it when planners use their schedules to lie.
It brings the entire industry into disrepute.
Member for
10 years 6 months@Aly Elasyed I agree with you
@Aly Elasyed
I agree with you that the Schedule % complete is generated automatically but my question is that "What are the ways to adjust Schedule % Complete on our desired percentage" out of the respect that the mean of software would be negligated. i need to show false schedule % complete
Member for
13 years 8 monthsDear,first what is the
Dear,
first what is the meaning of Schedule % Complete & Performance % complete in Primavera P6
Schedule % Complete means the percentage of elapsed time to the original time (dates wise) i mean if there is an activity with planned started 1apr2015 and planned finish 30apr2015 and the data date is 15apr2015, then the elapsed planned (scheduled) time to the planned duration (30 days) will be 50 %. it present the schedule % complete. if you have completed for example 50 % of the quantity of work, then your Performance % complete is 50 % then you are on schedule . but if you finished 40 % then your performance is 40 % but you have finished 50 % of your planned duration which means you are behind the schedule. and like that
Schedule % complete can't be changed as it automatically generated.
Regards,