Change in Lump Sum item

Member for

17 years 4 months

Thanks Larry, I also think like that.



Regards,

Omer

Member for

18 years

Omer,



Yes, Engineer can increase or decrease the amount of lump sum item through variation clause 51 of FIDIC 4th ED(1992).



The Clause 51 does not give any restriction to whether variation should be priced as LS, UP, Daywork, Cost plus, etc.



I suggest you check other part of your contract, such as special conditions or commercial clarification or price schedule (if any and as long as applicable), for clearer understanding of contract’s rule of pricing a variation.



Good day...