Forensic Claims Analysis Member for 18 years 6 months Member for 18 years 6 months Submitted by Oliver Melling on Fri, 2008-06-27 10:13 Permalink RE: Contract Programme revision upon award of EOT. Create an EOT impacted contract programme for use as the newly agreed baseline. Member for 22 years 5 months Member for 22 years 5 months Submitted by Christian Adri… on Fri, 2008-06-27 09:42 Permalink RE: Contract Programme revision upon award of EOT. I suppose you need to revise your tracking & control data as well... Log in or register to post comments
Member for 18 years 6 months Member for 18 years 6 months Submitted by Oliver Melling on Fri, 2008-06-27 10:13 Permalink RE: Contract Programme revision upon award of EOT. Create an EOT impacted contract programme for use as the newly agreed baseline.
Member for 22 years 5 months Member for 22 years 5 months Submitted by Christian Adri… on Fri, 2008-06-27 09:42 Permalink RE: Contract Programme revision upon award of EOT. I suppose you need to revise your tracking & control data as well...
Member for
18 years 6 monthsRE: Contract Programme revision upon award of EOT.
Create an EOT impacted contract programme for use as the newly agreed baseline.
Member for
22 years 5 monthsRE: Contract Programme revision upon award of EOT.
I suppose you need to revise your tracking & control data as well...