Time Impact Analysis (Prog Override vs. Retained Logic)

Member for

20 years 4 months

Actually,



My post will not help anyone in the project team. But it is real experience.



So go back to Post No. 3 by Andrew.



But the best advice is just blend with the project team, like a TIMANO of the Bourne Identity series.



I think this is one reason Primavera give this options. It will make us flexible and not dogmatic in our planning activities.



Remember, planning is only a tools. There are lots of controversy and issues on the way planning are implemented in particular project.



Cheers,



Sensei




Member for

20 years 4 months

HI,



Very interesting. I think depends on which side are you



The bright side, if your are in the contractor side



use retained logic to scare the project team in acting to mitigate delays, the top executive of the contractor are ignoramos always under the influence of commercial or contract department believing that claims for extension of time and associated cost will give them more profit than running the project as per baseline program or revised baseline program



use progress overide if the project teams are enligthen, the contract department influence in site activities are minimal to the point of zero, progress overide will also make way to upgrade the program into live and realistic schedule activities.



IF you are on the dark side, meaning, consultant, project manager, client. Always use retained logic to scare the contractor in doing there very best to achieve project goals.



Cheers,



Sensei

Member for

19 years 2 months

Hi,Hesham

progress override logic should be used for the horizontal projects like roads and infrastructures.

retained logic should be used for the vertical projects like Buildings.



THANKS