Delete "A" in Actual Dates Data

Member for

22 years 4 months

Yeah,

more over if during the updating of the program You also change some logic!!!



Is better to have a copy, as because is the baseline, with which You have to report Your actual progress against the planned.



Until You have not to re-schedule it.



Luca

Member for

23 years 8 months

That’s why I raise the question to Moises. If remove the actual date, some associate fields need review.

Member for

22 years 4 months

You can do exporting in excel the field you want to change as Activity ID, actual datesAcitivity ID You need as will be the reference when You will import back in P3 the file modified.

Make Your modification and then import on the new files.



Pay attention if your pourpose is to come back to some modification done, or make some what-if analysis, good but do not forget to modify also the percentage completed and/or the remaining duration.

Or you will have an activity pushed back to the run data!




Member for

23 years 8 months

May I know your purpose:

Do you want to display the date only (without "A") in actual date; or

Do you want to change an actual back to forcast one?

Member for

24 years 7 months

The “A” in the Early Start Date column may not be removed.



When the Actual Start Column is displayed then the “A” is not displayed but the Early Start of tasks are not displayed.



You could set up two Custom Data Items (CDI) and copy the Early Start and Early Finish columns to the two new CDIs and then display the CDIs as columns using Global Change. Don’t forget to run the Global Change each time you reschedule.



You are able to open a P3 schedule in SureTrak and then you my customize the character that indicates the actual start date and display a blank character.



Paul E Harris

Eastwood Harris Pty Ltd

Planning and Scheduling Book Publishers

www.eh.com.au




Member for

22 years 8 months

Try Global Change