SureTrak - Late dates / S- Curves

Member for

18 years 7 months

Hi, this is my first post reply



I will explain since(as,like) me I solve this problem.



First, inserted a column with "Constraint Finish Type"

Second, I select in the first activity "Constraint Finish Type = As late as possible".

Third. Whit "Copy Cell" I drag on all the activities and with "Paste Cell" paste in all the "As late as possible" value, for the column "Constraint Finish Type".

Last. I calculate this new situation and the result is the late curve.



I expect to have solved your problem.



I ask for excuses for my English, but only I write Spanish and to write this message have used a translator.