I would suggest go for your idea, experiment a lot, read books and involve in hands on planning using excel, P3, etc. Whatever knowledge you learn, keep on multiplying and improving you understanding of the secrets of planning. Along the way you will meet a master, planning master to guide you to perfection.
It is only then that you will find true meaning to the answers to your questions.
IMHO.
Cheers,
Charlie
Member for
20 years 5 months
Member for20 years5 months
Submitted by Raja Izat Raja… on Sun, 2006-07-23 10:53
Member for
20 years 4 monthsRE: resources managements
Hello Amin,
I would suggest go for your idea, experiment a lot, read books and involve in hands on planning using excel, P3, etc. Whatever knowledge you learn, keep on multiplying and improving you understanding of the secrets of planning. Along the way you will meet a master, planning master to guide you to perfection.
It is only then that you will find true meaning to the answers to your questions.
IMHO.
Cheers,
Charlie
Member for
20 years 5 monthsRE: resources managements
Hi
1.Yes for preliminary, parallel with that you have to identify the design change request or missing / over looked item which not include.
2.Use total item.
3.Either one could be use, depends on contract requirement.
4.Cost account / cash flow will base on unit rate, which followed by controlling milestone claim or monthly claim.
5.Dont have one, whatever my answer is from experience and actual practice at my company.
6.Not suitable time but u can PM me at anytime.
for further question, if u could tell me which area u are focusing either cost control or Planning Scheduling.
Regards