Thanks John & Neik for your Kind supporting comments.

Member for

21 years 5 months

To add to what Niek has outlined:



The PROJECT is the LOWEST level in the EPS and the HIGHEST level in the WBS. It therefore sits between the EPS and WBS.



HTH

Member for

20 years 7 months

Imran,



EPS is your WBS super structure and determines how you projects are grouped.



OBS is the hierarchical PM structure in your organisation and is linked to access rights in combination with the EPS.



Normally you don’t align EPS, OBS, WBS, and CAS because their are different structures that serve different purposes.



H.T.H.



Niek.