Oracle Primavera - PM6 Member for 18 years Member for 18 years Submitted by Imran Arshad on Fri, 2007-11-30 02:03 Permalink RE: P6 Thanks John & Neik for your Kind supporting comments. Member for 21 years 5 months Member for 21 years 6 months Submitted by John Raper on Thu, 2007-11-29 11:39 Permalink RE: P6 To add to what Niek has outlined: The PROJECT is the LOWEST level in the EPS and the HIGHEST level in the WBS. It therefore sits between the EPS and WBS. HTH Member for 20 years 7 months Member for 20 years 8 months Submitted by Niek Zonneveld on Thu, 2007-11-29 10:51 Permalink RE: P6 Imran, EPS is your WBS super structure and determines how you projects are grouped. OBS is the hierarchical PM structure in your organisation and is linked to access rights in combination with the EPS. Normally you dont align EPS, OBS, WBS, and CAS because their are different structures that serve different purposes. H.T.H. Niek. Log in or register to post comments
Member for 18 years Member for 18 years Submitted by Imran Arshad on Fri, 2007-11-30 02:03 Permalink RE: P6 Thanks John & Neik for your Kind supporting comments.
Member for 21 years 5 months Member for 21 years 6 months Submitted by John Raper on Thu, 2007-11-29 11:39 Permalink RE: P6 To add to what Niek has outlined: The PROJECT is the LOWEST level in the EPS and the HIGHEST level in the WBS. It therefore sits between the EPS and WBS. HTH
Member for 20 years 7 months Member for 20 years 8 months Submitted by Niek Zonneveld on Thu, 2007-11-29 10:51 Permalink RE: P6 Imran, EPS is your WBS super structure and determines how you projects are grouped. OBS is the hierarchical PM structure in your organisation and is linked to access rights in combination with the EPS. Normally you dont align EPS, OBS, WBS, and CAS because their are different structures that serve different purposes. H.T.H. Niek.
Member for
18 yearsRE: P6
Thanks John & Neik for your Kind supporting comments.
Member for
21 years 5 monthsRE: P6
To add to what Niek has outlined:
The PROJECT is the LOWEST level in the EPS and the HIGHEST level in the WBS. It therefore sits between the EPS and WBS.
HTH
Member for
20 years 7 monthsRE: P6
Imran,
EPS is your WBS super structure and determines how you projects are grouped.
OBS is the hierarchical PM structure in your organisation and is linked to access rights in combination with the EPS.
Normally you dont align EPS, OBS, WBS, and CAS because their are different structures that serve different purposes.
H.T.H.
Niek.