what we are doing is that from Resource assignment we transfer the data to Excel and plot the graph. This gives the room to plot the graphs on two vertical axis.
Cheers,
Arslan Usmani.
Member for
20 years 11 months
Member for20 years11 months
Submitted by Waseem Saber on Sun, 2007-12-16 16:30
this question has been raised with Primavera, this should be covered in P7 version "fingers Crossed", if you are so desperate, i would advice to export the data to any db and present your schedules....... this is more userfriendly and more graphical options..
cheers
Waseem Saber
Member for
18 years 1 month
Member for18 years2 months
Submitted by Johny Kesserwany on Tue, 2007-11-27 13:15
Member for
18 years 5 monthsRE: Showing numbers on Manpower Graph bars
Ijaz,
what we are doing is that from Resource assignment we transfer the data to Excel and plot the graph. This gives the room to plot the graphs on two vertical axis.
Cheers,
Arslan Usmani.
Member for
20 years 11 monthsRE: Showing numbers on Manpower Graph bars
Ijaz,
this question has been raised with Primavera, this should be covered in P7 version "fingers Crossed", if you are so desperate, i would advice to export the data to any db and present your schedules....... this is more userfriendly and more graphical options..
cheers
Waseem Saber
Member for
18 years 1 monthRE: Showing numbers on Manpower Graph bars
Hi Ijaz,
It seems that we cant !!! I already raised the issue with Primavera technical support and I wasnt able to display the values on the bars....
regards
jk