Showing numbers on Manpower Graph bars

Member for

18 years 5 months

Ijaz,



what we are doing is that from Resource assignment we transfer the data to Excel and plot the graph. This gives the room to plot the graphs on two vertical axis.



Cheers,



Arslan Usmani.

Member for

20 years 11 months

Ijaz,



this question has been raised with Primavera, this should be covered in P7 version "fingers Crossed", if you are so desperate, i would advice to export the data to any db and present your schedules....... this is more userfriendly and more graphical options..



cheers



Waseem Saber

Member for

18 years 1 month

Hi Ijaz,



It seems that we can’t !!! I already raised the issue with Primavera technical support and I wasn’t able to display the values on the bars....



regards

jk