Mark, this is very possible ith the My Primavera add on, Im currently doing this in the assignments view with a spreadshet, as this is how my resource managers like to see things. I havent tried the stacked histos in the client, but will be very interested in further posts here.
Member for
19 years 2 monthsRE: Stacked Histograms
Hi Mark
You must use myPrimavera Resource portlet to produce this kind of report.
In Resource portlet choose Resource Analysis. On Chart Type choose Stacked Histogram.
Then choose the resource you want and it will show resource loading grouped by project.
Thanks
Khuong
Member for
18 years 8 monthsRE: Stacked Histograms
Mark, this is very possible ith the My Primavera add on, Im currently doing this in the assignments view with a spreadshet, as this is how my resource managers like to see things. I havent tried the stacked histos in the client, but will be very interested in further posts here.