Stacked Histograms

Member for

19 years 2 months

Hi Mark

You must use myPrimavera Resource portlet to produce this kind of report.

In Resource portlet choose Resource Analysis. On Chart Type choose Stacked Histogram.

Then choose the resource you want and it will show resource loading grouped by project.



Thanks

Khuong

Member for

18 years 8 months

Mark, this is very possible ith the My Primavera add on, I’m currently doing this in the assignments view with a spreadshet, as this is how my resource managers like to see things. I haven’t tried the stacked histos in the client, but will be very interested in further posts here.



Andy