Baseline Units

Member for

18 years 5 months

Thanks peeps! I will have a look at that thanks again :0)



Happy planning :0)

Member for

18 years 8 months

Kenny,

If you have run a report on Budgeted units it may very well be different to the baseline. The way Primavera uses the words Budget and basline can be confusing.



From my use of the tool the budgeted labor or non-labor units can be modified without regard to the baseline.



If you are going to run a report as you suggest, you need to run it on ’BL Project Labor/Non-labour Units’ which will be the approved baseline budget.



I have simply removed all of the ’Budget’ data from my views so I don’t get confused. I have also asked for a clarification from Primavera to explain their resons for calling the budget information budget, when all I’ve ever known as a budget is the approved baseline.



I’ll post their comments here if and when I get them.





Andy

Member for

18 years 9 months

Hi Kenny



Baselines are not touched by modifications of the main project.

I am afraid that I didn’t 100% understand your item. Did you check under Admin --> Preferences --> Earned Value the Earned Value Calculations. There might be the reason for your modified data.

Regards

Dieter