If you have run a report on Budgeted units it may very well be different to the baseline. The way Primavera uses the words Budget and basline can be confusing.
From my use of the tool the budgeted labor or non-labor units can be modified without regard to the baseline.
If you are going to run a report as you suggest, you need to run it on BL Project Labor/Non-labour Units which will be the approved baseline budget.
I have simply removed all of the Budget data from my views so I dont get confused. I have also asked for a clarification from Primavera to explain their resons for calling the budget information budget, when all Ive ever known as a budget is the approved baseline.
Ill post their comments here if and when I get them.
Andy
Member for
18 years 9 months
Member for18 years10 months
Submitted by Dieter Wambach on Thu, 2007-06-28 06:49
Baselines are not touched by modifications of the main project.
I am afraid that I didnt 100% understand your item. Did you check under Admin --> Preferences --> Earned Value the Earned Value Calculations. There might be the reason for your modified data.
Member for
18 years 5 monthsRE: Baseline Units
Thanks peeps! I will have a look at that thanks again :0)
Happy planning :0)
Member for
18 years 8 monthsRE: Baseline Units
Kenny,
If you have run a report on Budgeted units it may very well be different to the baseline. The way Primavera uses the words Budget and basline can be confusing.
From my use of the tool the budgeted labor or non-labor units can be modified without regard to the baseline.
If you are going to run a report as you suggest, you need to run it on BL Project Labor/Non-labour Units which will be the approved baseline budget.
I have simply removed all of the Budget data from my views so I dont get confused. I have also asked for a clarification from Primavera to explain their resons for calling the budget information budget, when all Ive ever known as a budget is the approved baseline.
Ill post their comments here if and when I get them.
Andy
Member for
18 years 9 monthsRE: Baseline Units
Hi Kenny
Baselines are not touched by modifications of the main project.
I am afraid that I didnt 100% understand your item. Did you check under Admin --> Preferences --> Earned Value the Earned Value Calculations. There might be the reason for your modified data.
Regards
Dieter