P3e uses the fields Planned Start and planned Finish as the basis of the baseline. This works fine for activities with no progress, but not so good for completed and especially in-progress activities.
Use Global Change to set Planned Start/planned Finish equal to Start/Finish.
Member for
19 years 7 monthsRE: P3 e/c Baseline
thanx
Member for
23 yearsRE: P3 e/c Baseline
P3e uses the fields Planned Start and planned Finish as the basis of the baseline. This works fine for activities with no progress, but not so good for completed and especially in-progress activities.
Use Global Change to set Planned Start/planned Finish equal to Start/Finish.