P3 e/c Baseline

Member for

19 years 7 months

Member for

23 years

P3e uses the fields Planned Start and planned Finish as the basis of the baseline. This works fine for activities with no progress, but not so good for completed and especially in-progress activities.



Use Global Change to set Planned Start/planned Finish equal to Start/Finish.