Activity Weighting Parameter

Member for

19 years 10 months

Hi Razvan
Alternatively present only tasks for one trade in one location no more than 10 working days and you will not need any weighting.
Best regards
Mike Testro

Member for

16 years 3 months

simply assign the necessary manhours to perform each activity. The total of all of the manhours for ALL activities should total what you have estimated and therefore each one of the task is weighted in its self.

The monthly total of the manhours will give you a histogram for the required manpower and the cumulative monthly manhours  will give you and S curve that at the end total ALL of your manhours.

Member for

21 years 8 months

Consider using Weight Parameter as a user defined field to calculate Earned Value.

EVM_using_weight_parameter