Hi Razvan
Alternatively present only tasks for one trade in one location no more than 10 working days and you will not need any weighting.
Best regards
Mike Testro
Member for
16 years 3 months
Member for16 years3 months
Submitted by Zoltan Palffy on Mon, 2018-03-26 14:51
simply assign the necessary manhours to perform each activity. The total of all of the manhours for ALL activities should total what you have estimated and therefore each one of the task is weighted in its self.
The monthly total of the manhours will give you a histogram for the required manpower and the cumulative monthly manhours will give you and S curve that at the end total ALL of your manhours.
Member for
21 years 8 months
Member for21 years8 months
Submitted by Rafael Davila on Sun, 2018-03-25 01:29
Member for
19 years 10 monthsHi Razvan Alternatively
Hi Razvan
Alternatively present only tasks for one trade in one location no more than 10 working days and you will not need any weighting.
Best regards
Mike Testro
Member for
16 years 3 monthssimply assign the necessary
simply assign the necessary manhours to perform each activity. The total of all of the manhours for ALL activities should total what you have estimated and therefore each one of the task is weighted in its self.
The monthly total of the manhours will give you a histogram for the required manpower and the cumulative monthly manhours will give you and S curve that at the end total ALL of your manhours.
Member for
21 years 8 monthsConsider using Weight
Consider using Weight Parameter as a user defined field to calculate Earned Value.