Budgeted cost extends beyond the project finish date.

Member for

17 years 4 months

Hi Renjith,

In the spread sheet, add rows for Earned Value and the Estimate to Complete.

In the overall WBS for the Project, select ETC=PF*(BAC-EV), where PF=1

 

If you select the Budgeted Cost in the spread sheet, it will be calculated based on the Planned values, which may confuse you.

Best Regards

Kannan