Planning, Scheduling & Programming Discussion Member for 17 years 4 months Member for 17 years 5 months Submitted by Kannan CP on Sun, 2018-03-04 09:38 Permalink Hi Renjith,In the spread Hi Renjith, In the spread sheet, add rows for Earned Value and the Estimate to Complete. In the overall WBS for the Project, select ETC=PF*(BAC-EV), where PF=1 If you select the Budgeted Cost in the spread sheet, it will be calculated based on the Planned values, which may confuse you. Best Regards Kannan Log in or register to post comments
Member for 17 years 4 months Member for 17 years 5 months Submitted by Kannan CP on Sun, 2018-03-04 09:38 Permalink Hi Renjith,In the spread Hi Renjith, In the spread sheet, add rows for Earned Value and the Estimate to Complete. In the overall WBS for the Project, select ETC=PF*(BAC-EV), where PF=1 If you select the Budgeted Cost in the spread sheet, it will be calculated based on the Planned values, which may confuse you. Best Regards Kannan
Member for
17 years 4 monthsHi Renjith,In the spread
Hi Renjith,
In the spread sheet, add rows for Earned Value and the Estimate to Complete.
In the overall WBS for the Project, select ETC=PF*(BAC-EV), where PF=1
If you select the Budgeted Cost in the spread sheet, it will be calculated based on the Planned values, which may confuse you.
Best Regards