Delayed completion

Member for

16 years 3 months

glad we could help 

Member for

12 years

Thanks Mike Testro & Zoltan for your valuable feedback, that was helpful.

Member for

16 years 3 months

ok you now have a measured mile so base your duration on this measure mile for activities not yet started

Member for

19 years 10 months

Hi Ayman

Even in P6 you can run a filter on the task and do a global change - 10 minutes max.

Save the original file first.

Best regards

Mike Testro

Member for

12 years

Zoltan Palffy Thanks for your reply,  1 Node represents 300m of pipe line (single) and in this case its double line means 600m, in the past we have completed 500m of twin(means 1000m) line easily with in 1 day. Considering previous progress this activity completion shall take one more day to complete or should have remaining duration 1 day.

Member for

16 years 3 months

it happens because you originally OVER ESTIMATED the duration. Where did the original duration come from ? What is the basis for the original duration and what is the basis for the statement that it will only take 1 day. Is there any quantiies assoicated with this taks is it Bedding for 5 square yards or for 5,000 squarte yards ? Is there any historical information based on this type of work within your company ? 

The way to resolve it is to get good defendable duraitons when you create the schedule.