Zoltan Palffy Thanks for your reply, 1 Node represents 300m of pipe line (single) and in this case its double line means 600m, in the past we have completed 500m of twin(means 1000m) line easily with in 1 day. Considering previous progress this activity completion shall take one more day to complete or should have remaining duration 1 day.
Member for
16 years 3 months
Member for16 years3 months
Submitted by Zoltan Palffy on Mon, 2017-07-10 14:22
it happens because you originally OVER ESTIMATED the duration. Where did the original duration come from ? What is the basis for the original duration and what is the basis for the statement that it will only take 1 day. Is there any quantiies assoicated with this taks is it Bedding for 5 square yards or for 5,000 squarte yards ? Is there any historical information based on this type of work within your company ?
The way to resolve it is to get good defendable duraitons when you create the schedule.
Member for
16 years 3 monthsglad we could help
glad we could help
Member for
12 yearsThanks Mike Testro & Zoltan
Thanks Mike Testro & Zoltan for your valuable feedback, that was helpful.
Member for
16 years 3 monthsok you now have a measured
ok you now have a measured mile so base your duration on this measure mile for activities not yet started
Member for
19 years 10 monthsHi AymanEven in P6 you can
Hi Ayman
Even in P6 you can run a filter on the task and do a global change - 10 minutes max.
Save the original file first.
Best regards
Mike Testro
Member for
12 yearsZoltan Palffy Thanks for your
Zoltan Palffy Thanks for your reply, 1 Node represents 300m of pipe line (single) and in this case its double line means 600m, in the past we have completed 500m of twin(means 1000m) line easily with in 1 day. Considering previous progress this activity completion shall take one more day to complete or should have remaining duration 1 day.
Member for
16 years 3 monthsit happens because you
it happens because you originally OVER ESTIMATED the duration. Where did the original duration come from ? What is the basis for the original duration and what is the basis for the statement that it will only take 1 day. Is there any quantiies assoicated with this taks is it Bedding for 5 square yards or for 5,000 squarte yards ? Is there any historical information based on this type of work within your company ?
The way to resolve it is to get good defendable duraitons when you create the schedule.