I would recommend using as planned value, as if you are mitigating by using additional resources, which I assume is how you have adjusted your productivity, or longer working hours per period etc, your at complete cost will go up, so you need to compensate somehow.

50% of $100 is $50 so 50%, but 50% of your now $120 is not $50 anymore, if that makes sense.