I would recommend using as planned value, as if you are mitigating by using additional resources, which I assume is how you have adjusted your productivity, or longer working hours per period etc, your at complete cost will go up, so you need to compensate somehow.
50% of $100 is $50 so 50%, but 50% of your now $120 is not $50 anymore, if that makes sense.
Member for
15 years 2 monthsI would recommend using as
I would recommend using as planned value, as if you are mitigating by using additional resources, which I assume is how you have adjusted your productivity, or longer working hours per period etc, your at complete cost will go up, so you need to compensate somehow.
50% of $100 is $50 so 50%, but 50% of your now $120 is not $50 anymore, if that makes sense.
Member for
10 yearsDear Sir...Kindly tell me how
Dear Sir...
Kindly tell me how to calcaulte the planned % and actual % and time elapsed of project. with example...
I am waitng your positive response ..
With Regards
Nadeem